When are Schluter and Healy going to be done?
"The project seems to be moving slow because all the work up to this point has been associated with underground utility work, which is a time consuming process. The contractor will be starting on the actual road improvements this week. This will include new curb and gutter on Schluter Road, spot replacement of curb and gutter on other affected streets, and the reconstruction of the street structure itself. This process will take us into mid-October, when final paving of the streets is scheduled to occur. Richard R. Vela, P.E.City Engineer/Director of Public Works"
Wednesday, September 19, 2007
Subscribe to:
Post Comments (Atom)
Does that mean they'll finally be starting on Arrowhead Drive?
ReplyDeleteI drove by after seeing your comment and then called the city engineer and I'll let you know what I find out.
ReplyDeleteArrowhead is only street reconstruction work with new curb and gutter, but no utility work so it will go much faster.
The new location of the basketball court is also staked out.